2011
Janury
This month we started supplying the regulated consumption of Chilectra power distributor as a result of the enforcement of the contract awarded in 2007, which involves an annual supply of approximately 2,500 GWh.t
February…
Read More...
-
2010
January
The first bond is emitted in international markets for US$ 500 million at a placement rate of 6,139 a year for a period of 10 years. The bond has a “bullet” structure with monthly…
Read More...
-
2009
January
Begins the application of International financial information norms (NIIF) and the US dollar is adopted as functional currency.
In the frame of the distributing company’s tenders, Colbún is awarded with supply contracts with CGED for…
Read More...
-
2008
January
Hornitos Hydroelectric Central enters service.
February
The first decree for electric rationing is promulgated for the year 2008.
July
Two projects are registered before the Clean Development of the United Nations Director’s Board: The hydroelectric centrals of Quilleco…
Read More...
-
2007
May
Dual operation (natural gas and diesel oil) of Nehuenco II Central starts working.
June
Quilleco hydroelectric Central enters service.
The Corema of the Bío Bío region approves the Environmental Impact Study of the project “Santa María I…
Read More...
-
2006
May
Tractebel sell their entire share in Colbún S.A.
In this sale Antarchile S.A. society, related to the Angelini Group, purchases a 9,53% of the property of Colbún S.A.
August
A society is created for the development of…
Read More...
-
2005
August
Energy market: Matte contributes to Colbún US$ 750 Millions in active.
Santander Investment and Bear Stearn foresee that their patrimony will grow over 50% after their fusion with Minera Valparaíso.
August
Colbún becomes the second electric actor…
Read More...
-
2004
May
Combined Cycle Thermal Central Nehuenco is operative.
-
2003
May
Colbún started phase one in Nehuenco Central II.
August
The company signs a contract for the supply of Conafe, that will be effective from May, 2005.
October
Conama council of ministers authorizes the Candelaria Central Project in the…
Read More...
-
2002
June
Commercial operation of open cycle thermal central Nehuenco III starts.
-
2001
July
A supply agreement with Codelco is reached.
September
Corfo sells the major part of their stock in the local stock market and the company changes its name to Colbún S.A.
-
1999
April
Failures in Nehuenco I force stopping its operation for repair.
August
Central Nehuenco I is functioning again and is reconnected to the Interconnected Central System (SIC).
-
1998
April
Hydroelectric Central Rucúe enters service.
November
Combined Cycle Thermal Central Nehuenco I starts operating.
-
1996
October
Corfo stops controlling the company by selling 37% of their share in Colbún Machicura Electric Company S.A.
November
Hydroelectric Central San Ignacio starts working.
-
1993
March
Colbún signs the biggest contract in its history with Chilectra: US$ 300 Million for seven years.
-
1989
December
Corfo announces the sale of all its Colbún stock. The titles correspond to 99% of the hydroelectric company capital.
-
1987
November
Colbún Machicura S.A. inaugurates in the 7th region of Maule three great works destined to improve and secure the irrigation of 46 thousand hectare of farming soil (San Clemente Canal, Maitenes System and…
Read More...
-
1986
April
Starting from the division of National Electric Company S.A., Endesa; Colbún Machicura Electric Company S.A. was created as a subsidiary of Corfo.
-
1985
June
Colbún-Machicura Complex starts delivering energy. Trial period.
July
The hydraulic centrals of Colbún and Machicura start working.
September
The hydraulic centrals of Colbún and Machicura are inaugurated.
-
1984
December
The giant Colbún-Machicura starts filling the reservoir. One thousand five hundred millions cubic meters of water will be accumulated until March 1st, 1985.
-
1983
April
The construction of Colbún –Machicura begins, constituted by Colbún and Machicura centrals.
-
1979
August
Endesa announces pre qualification for companies interested in building the Colbún-Machicura Complex. Tender was formalized at the beginning of 1980